KGL Jervois Project Feasibility Study Update 2025
Released
Released
Announcement PDF
KGL Announces Feasibility Study Update and
plans to progress to production in 2027
10 February 2025
The attached announcement contains:
1. Highlights of the Feasibility Study Update and next steps.
2. The Executive Summary of the Jervois Feasibility Study Update.
3. The Jervois Project Ore Reserve Statement prepared by Xenith Consultants.
This announcement is authorised by the KGL Resources Limited Board of Directors.
Cautionary Statement
The Feasibility Study referred to in this announcement has been undertaken to determine the potential viability
of development of the Jervois Copper Project. The production target for the Jervois Copper Project is based
on (Proved and Probable) Ore Reserves of 86.7% and 13.3% Inferred Mineral Resources.
There is a low level of geological confidence associated with Inferred Mineral Resources and there is no
certainty that further exploration work will result in the determination of Indicated Mineral Resources or that the
production target will be realised.
The Ore Reserve and Mineral Resource estimates underpinning the production targets were prepared by
Competent Persons in accordance with the JORC Code 2012.
The production target and forecast financial information derived from the production target set out in this
release (supported by the Feasibility Study Update) are based on the material assumptions outlined in
Feasibility Executive Summary.
While KGL Resources considers all the material assumptions to be based on reasonable grounds, there is no
certainty that they will prove to be correct or that the range of outcomes indicated by the studies will be
achieved.
Given the uncertainties involved, investors should not make any investment decisions based solely on the
results of these studies.
Page 1 of 9
KGL Announces Feasibility Study Update and
plans to progress to production in 2027
KGL Resources Limited today announced the results of the Feasibility Study Update
(FSU25) and its intention to move ahead with Project financing plans and operational
readiness works.
The findings of the Feasibility Study Update confirmed that the Jervois Copper Project is technically
robust and financially viable. The project NPV is A$405 million with an attractive capital efficiency of
~A$12,000/t contained copper per annum., and a simple payback of around 3.4 years.
Executive Chairman, Jeff Gerard commented
“The release of the Feasibility Study Update is the foundation to deliver a new mining hub for critical and
strategic minerals within the Northern Territory in the eastern Arunta region.
The Jervois Copper Project is a technically feasible, economically and environmentally sound mining
operation leveraged to the global copper price. We have optimised the mine plan, updated the capital and
operating costs estimates, and de-risked the project. The FSU25 contained copper resource has increased
by 8.0% to 510,0001 tonnes and the proportion of open cut ore increased from 25% to 41% of total ore
mined. Proven ore reserves from the open pit are mined and processed through the plant over 4 years.
During this time, the operations are able to transition to underground ore feed to the plant.
KGL is well positioned with all necessary approvals, to deliver its high-grade Jervois project into a copper
market at a time of a projected chronic global supply shortfall bringing opportunities for jobs and economic
development to the Northern Territory, ensuring sustainable operations and delivering long-term value to
stakeholders.”
Highlights
Project Value
•
Net Present Value (NPV8) A$405M (post-tax), NPV8 of A$601M (pre-tax)2
•
Internal Rate of Return (IRR) of 24%.
•
C1 cost US$1.95/lb (by-product basis, during 7 years of steady state).
•
Simple payback 3.4 years based on peak cash drawdown of A$497m (from 1st
concentrate).
• Average operating cashflow A$208 million per annum (steady state).
Scale and Opportunity
•
Stage 1 (FSU 25) 10 year mine life lays the foundation for future low cost / accretive
growth opportunities based on substantial potential for Resource and Ore Reserve
growth.
Production
•
Commissioning and ramp-up during H1 2027 with steady state throughput capacity from
mid-2027.
•
Ore Reserves: Total Proven and Probable Reserves of 14.38 Mt @ 1.77% Cu,
containing 265 kt of copper, 9.4 Moz silver and 76.1 koz gold supporting average annual
steady state production: Cu ~30kt pa, Ag ~1,016 koz pa and Au ~8.9 koz pa.
•
Construction Capital Cost estimate A$362 million.
Capital
1 May 2024 Mineral Resource Estimate adjusted
2 8% Real Discount Rate, after tax
Page 2 of 9
KGL Announces Feasibility Study Update and
plans to progress to production in 2027
Highlights (cont.)
Contribution
•
Peak employment by KGL and Contractors of up to 450 people during construction and
up to 500 people during operations supported by a 300-man camp.
•
NT royalty contribution c.A$220M.
Concentrate Offtake
•
An updated offtake contract for copper concentrate, including by-products, is being
finalised.
Regulatory Approvals
•
Key approvals in place to allow for the commencement of development and operation.
Next Steps
•
Appointment of a financial advisor, assessment of the optimal financing structure of the
project and negotiations with potential equity and debt investors.
•
Finalise Project Execution Plan in advance of key appointments and negotiation of
significant contracts with Tier 1 contractors.
•
RPM Advisory Services Pty Ltd (RPM) is targeting completion of the Independent
Technical Engineers (ITE) Report and Independent Environmental and Social Report
(IESR) acceptable for the purpose of project financing, during H1, 2025.
Page 3 of 9
KGL Announces Feasibility Study Update and
plans to progress to production in 2027
FSU25: Project Overview
The Jervois Copper Project Feasibility Study Update 2025 (FSU 25) is the result of optimisation works and
ongoing project derisking following the maiden Feasibility Study issued at the end of 2022.
The FSU 25 continues to define a robust project with a 10-year life of mine plan.
During the first seven years of the production schedule, post operational ramp up, the project delivers an
average of 30 kt per annum of copper in concentrate at an average C1 cost of US$1.95/lb (after by-products)
generating average EBITDA of approximately $229M per annum (steady state).
Overall, the Project’s after-tax net present value at a discount rate of 8% has increased from A$241M to
A$405M (c.68%). The Project has an attractive capital efficiency of c.A$12,000 per tonne of contained copper
per annum3, with a simple payback of c.3.4 years from first concentrate.
The Project is based on a high-grade Reserve, 1.77% copper, with silver and gold credits. The Project has an
18-month construction schedule followed by a 6-month plant commissioning and ramp up program to achieve
forecast concentrate production during 2027 (subject to completing satisfactory financing arrangements). The
Company currently has zero debt.
Initially all ore production will be from conventional contractor managed open cut operations delivering 2Mtpa
(ore feed). This is followed by progressively developing underground mines to transition from open pit to full
underground feed by mid-2030, as planned open pit ore finishes. The purpose-built, state of the art,
concentrator, with a nameplate capacity of 2 million tonne ore feed per annum, is designed to produce 27%
copper / byproducts concentrate, that is sold under a Free on Transport (FOT) / ex-site commercial offtake
contract.
Detailed technical, environmental and commercial studies indicate the project can be built and operated with
low operating costs, manageable technical risks, minimal environmental impact with positive economic and
social outcomes.
Project Value & Sensitivity
Based on current market forecasts, the Project is expected to generate an after-tax net present value at a
discount rate of 8% of A$405M. KGL believes the Jervois Project is timed to deliver copper into the potential
supply deficit where increased commodity / incentive prices will prevail. The FSU 25 does not reflect supply
deficit pricing however the upside economics facing the Project, once delivered, are significant.
3 Based on total initial capital cost of A$362M and annual copper production during steady state of 30ktpa.
Page 4 of 9
KGL Announces Feasibility Study Update and
plans to progress to production in 2027
Table 1: Project key sensitivities
Copper Price
FS 2022
FSU 25
Incentive
price
assumption
“Bullish price
forecast”
US$/lb
4.23
4.581
5.90
6.80
US$/t
9,370
10,094
13,000
15,000
Exchange Rate
A$:US$
0.70
0.64
0.70
0.70
NPV 8% (real, before tax)
A$M
372
601
992
1,413
NPV 8% (real, after tax)
A$M
241
405
682
978
IRR (before tax)
%
28%
30%
41%
52%
IRR (post tax)
%
21%
24%
33%
42%
Years
4.2
3.4
2.7
2.1
Simple Payback Period (1st Conc.)2
1.
2.
Bloomberg Brokers Consensus (avg.) and London Metals Exchange Forecast to 2027 - US$4.58/lb / US$10,100/t
1.5 years of construction period before 1st concentrate.
Study Outcomes
The key financial metrics for the FSU 2025 and FS 2022 are as follows:
Table 2 Project key financial metrics
Metric
Unit
FS 2022
FSU 25
Life of Mine Net Revenue
A$ billion
$3.67
$4.44
Life of Mine EBITDA
A$ billion
$1.38
$1.86
Payable Copper
kt
267.4
255.7
Payable Gold
k oz
59.1
68.5
Payable Silver
M oz
8,454.5
8,497.4
Reserve
MT
11.73MT @2.10% Cu,
0.29 g/t Au & 29.8 g/t Ag
14.38MT @1.77% Cu,
0.26 g/t Au & 26.27 g/t Ag
CU concentrate (LOM)
kdmt
1,028
983
Cu recovery (Sulphide)
%
92.2
92.0
C1 Cost (US$/Ib Cu eq) (steady state)
US$/Ib
$2.22
$1.95
C1 Cost (US$/lb Cu eq) LOM
US$/lb
$2.35
$2.19
AISC (US$/lb) (steady state)
US$/lb
$3.13
$2.86
Average Cu in concentrate production
(steady state)
ktpa
27
30
Construction Capex
A$ million
298
362*
Copper Price
US$/lb
4.23
4.58
Gold Price
US$/oz
1,735
2,668
Silver Price
US$/oz
22.70
32.62
FX AU$:US$
US$
0.70
0.64
Page 5 of 9
KGL Announces Feasibility Study Update and
plans to progress to production in 2027
Diesel (ex GST and Fuel Tax Credits)
A$/L
1.30
1.30
Electricity
c/kWh
24.49
29.76
%
8%
8%
Net Present Value (pre-tax)
A$ million
$372
$601
Net Present Value (post-tax)
A$ million
$241
$405
Internal Rate of Return (pre-tax)
%
28.5
30.4
Internal Rate of Return (post-tax)
%
20.7
24.3
Discount Rate (real)
*Includes airstrip of $20m. FS2022 has provisions for Drive-In Drive-Out ex-Alice Springs.
On a gross revenue basis, copper contributes approximately 84%, whilst gold and silver by-products
contribute circa 6% and 10%, respectively.
Following the ramp up of the plant to design throughput capacity (mid 2027), the average EBITDA is $229
million per annum.
Scale and Opportunity
The FSU 25 10-year mine life lays the foundation for low cost / accretive growth. Substantial potential exists
for Resource and Ore Reserve growth, leading to increased utilisation of the installed plant capacity and mine
life extension. The Jervois tenements remain under explored with recent drilling focused on infill drilling and
extending the resource and knowledge, at depth, for the current lodes. This work has consistently
demonstrated high grade copper intersects in these areas. Structural geology and geophysical interpretations
of existing exploration information are providing key targets for future exploration programs.
Key improvements since FS November 22
In the period following the release of FS22, KGL has been able to embed numerous improvements including:
1.
2.
3.
4.
5.
6.
An updated 2024 Mineral Resource and Ore Reserve estimate.
Improved Resource confidence, for open cut mining, over the first 4 years of the project.
Increased open-cut mining tonnages in first 3 years.
Reduced proportion of Inferred Resources in the mine plan.
Increased the proportion of lower risk open cut mineable reserves.
Increased open cut productivity by the selection of larger capacity mining fleet and obtaining an
approval for a shorter haul to Reward south dump.
7. Increased Concentrator plant nameplate capacity from 1.6Mtpa to 2.0Mtpa.
8. Updated the proportion of primary mined ore and stoped ore.
9. Increased Mineral Resource tonnages at depth.
10. Updated Infrastructure and civil works scopes including the addition of a dedicated airstrip.
Contribution
The Jervois Project (both KGL and Contractors) will provide peak employment of 450 people during
construction and up to 500 people employed during operations supported by a 300-man camp. The NT royalty
contribution is c.A$220M.
Concentrate Offtake and Income Security
An updated contract for the offtake of up to 1Mt of copper concentrate is currently being re-negotiated. The
payment terms of the concentrate will be Free on Transport (FOT). Provision for advance payments is
included in the contract.
Page 6 of 9
KGL Announces Feasibility Study Update and
plans to progress to production in 2027
By-product credits for gold and silver represent approximately 16% of the gross revenue. The offtake contract
also includes revenue adjustments for payable metals, TC/RC’s, contaminant penalties and freight charges.
The only penalty parameter triggered is for Bismuth which represents less than 1% of the gross revenue.
There are no rejection criteria under the contract.
Regulatory Approvals
Mining tenements remain in good stead and key approvals are in place to allow for the commencement of
development and operation. These include, but not limited to, Jervois Project ILUA and clearance,
Authorisation 1061-1, Mining Management Plan and various water licenses and permits.
Sustainability and Environmental Plans
KGL is committed to sustainable mining practices, emphasising environmental stewardship and community
engagement.
•
Renewable Energy: At least 60% of power needs are planned to be met by a dedicated hybrid power
station that incorporates solar, wind and battery storage to reduce on site greenhouse gas emissions.
•
Tailings Management: Engineered HDPE-lined storage facility with staged embankments ensures longterm environmental containment.
•
Water Management: Water recycling is designed for process water to maximise reuse and minimise raw
water consumption and cost.
•
Closure and Rehabilitation: Progressive reclamation plans align with NT Government requirements,
ensuring minimal ecological disruption and restoration to the pre-existing or improved land use /
capability.
Next Steps & Additional Project Optimisation Opportunities
A Phase 1 Independent Technical Review has been completed by RPM showing no red flag / critical issues.
Lower-level risk issues (not Red Flags) have been included in the Company Risk Register with risk mitigations
initiatives scheduled accordingly.
RPM have been engaged to complete Phase 2 that involves an Independent Technical Engineers (ITE)
Report and Independent Environmental and Social Report (IESR) suitable for the purpose of project financing.
This is targeted to be completed during H1, 2025.
KGL will appoint a financial advisor to assist with assessing the optimal capital structure for the Jervois project
and negotiations with equity and debt investors.
Priority activities to advance the Project include:
•
Expand the owners / project delivery teams consistent with the Project Execution Plan.
•
Finalise water, power, and services agreements.
•
Finalise contracts for site preparation civil works, plant EPC and open pit operations.
•
Progress funding agreements.
Future optimisation opportunities, separate to Project delivery, include
•
Capital reduction: Scope exists to further rationalise and reduce elements of the construction capital in
the areas of civil works, village construction and the airstrip. This will be updated as part of the enabling
/ early works activities.
Page 7 of 9
KGL Announces Feasibility Study Update and
plans to progress to production in 2027
•
Construction schedule: Enabling / Early works, prior to a Financial Investment Decision (FID) is being
considered to reduce the project delivery timeline risk for selected critical path activities which may also
provide increased project time contingency.
•
Resource Expansion: Additional open pit resources have been identified that can be brought into the
mining schedule to improve the open pit utilisation of equipment and improve the access and
development cost of selected underground areas at Bellbird and Reward.
•
Polymetallic Recovery: Assessment of lead and zinc resources is a significant study that will be
progressed during project construction and operation to further extend the life of the project and the
incremental utilisation the installed capital and operating equipment to enhance project economics.
Timeline
Subject to finance, delivery of first concentrate is targeted H1 2027. Steady-state operations is expected H2
2027 delivering an average 30kt per annum of contained copper in a 27% saleable copper concentrate per
annum.
Page 8 of 9
KGL Announces Feasibility Study Update and
plans to progress to production in 2027
Market Timing
Wood Mackenzie reported in a recent article (August 2024) that “The world cannot decarbonise without
copper, a key component of electrification. Amid efforts to secure minerals for the energy transition and
achieve climate goals, demand is set to surge. We estimate that demand for copper will grow by 75% to 56
million tonnes (Mt) by 2050. Meeting this demand will require major investment.”
Ongoing decarbonisation via renewable generation, grid expansion, electric vehicles, technology
advancement (AI and data centres) and military demand, support the demand growth whilst headwinds
continue to impact the supply side that creates the expected supply / demand gap.
Macro-economic impact such as inflation and supply chain disruptions that were occurring, at the time the
2022 feasibility study was released, have abated.
A report titled Copper Price 2024-End Review (Dec 30, 2024), from Investing News Network concluded;
“Copper demand is still constrained by weakness in the Chinese economy, particularly in its housing sector,
which is an important driver of global demand for the metal. Ultimately, in the longer term, copper supply will
be lacking from new projects and expanded production to meet demand. The base metal is expected enter a
supply deficit over the next few years.”
In a recent interview at the Future Minerals Forum in Riyadh (FMF25), Codelco Chairman Maximo Pacheco
expressed optimism about the future of copper, noting its critical role in the global energy transition. "If you
believe that the world of the future will be more electrical, the best conductor of electricity is copper," he stated.
The increasing demand for copper will drive prices higher, he added. “The world needs more copper and it's
obvious to me that if there is a strong demand of copper, that means that the world will pay for it.”
Page 9 of 9
Jervois Copper Project
Feasibility Study Update
1
EXECUTIVE SUMMARY
The Jervois Copper Project (the Project) is in the Northern Territory (NT) of Australia approximately
380km by road, east-north-east of Alice Springs, within existing Mineral Leases, on the Jervois
Pastoral Lease owned by Jervois Pastoral Company Pty Ltd (a non-KGL Resources Limited (KGL)
related entity). The groundwater borefield related Mineral Lease is located around 20km from the
project, on the approval of Lucy Creek Station owned by the Lucy Creek Pastoral Company, (also a
non-KGL entity). The project is polymetallic (copper, silver, gold) that is primarily leveraged to the
price of copper and AUD: USD exchange rate. Additional potential by-products including lead, zinc
and other payable metals have not been considered in the project.
The Project Feasibility Study Update January 2025 (FSU 2025) has been prepared by KGL with
inputs and support of consultants, suppliers and contractors. RPM Advisory Services Pty Ltd has
completed the Phase 1 Independent Technical Review with no critical / red flag issues identified.
Phase 2 of the review will entail an Independent Technical Engineers report and Independent
Environmental and Social Report for the purposes of financing arrangement. This is expected to be
completed during H1 2025. The key financial metrics for the FSU 2025 are as follows:
Table 1-1: Project key financial metrics
Metric
Unit
Value
Copper Price*
US$/lb
$4.58
Gold Price*
US$/oz
$2,668
Silver Price*
US$/oz
$32.62
Exchange Rate
A$:US$
$0.64
%
8%
Net Present Value (pre-tax)
A$ million
$601
Net Present Value (post-tax)
A$ million
$405
Internal Rate of Return (pre-tax)
%
30.4%
Internal Rate of Return (post-tax)
%
24.3%
Project Payback peak funding (from 1st concentrate)
Years
3.4
Life of Mine
Years
10
Life of Mine Ore
kt
16,591
Average Copper per annum (steady state)
ktpa
30
Process Plant nameplate capacity
Mtpa
2.0
Life of Mine Net Revenue
A$ billion
$4.437
Life of Mine EBITDA
A$ billion
$1.858
Life of mine free cashflow (pre-tax)
A$ billion
$1.183
Life of mine free cashflow (post-tax)
A$ million
$873
C1 Cost (US$/Ib Cu eq) (steady state)
US$/Ib
$1.95
Construction Capital Cost estimate
A$ million
$362
Peak Funding including Development Opex
A$ million
$497
Discount Rate (real)
Source: * Bloomberg Consensus – Oct/Dec 2024
KGL RESOURCES LIMITED
Page 1
Jervois Copper Project
Feasibility Study Update
On a gross revenue basis, copper contribute approximately 84%, whilst gold and silver by-products
contribute circa 6% and 10%, respectively.
The Feasibility Study Update with an NPV of circa $405m demonstrated that the Jervois Copper
Project is technically and financially viable, and a robust project notwithstanding the normal macroeconomic impacts from exchange rate, commodity price and inflation.
The feasibility study update has been estimated to a Class 4 estimate category (AusIMM guidelines)
to a level of definition and accuracy in the range of +/-15% basis Q4 2024.
1.1
Project overview
Exploration in the Jervois Range first commenced in 1929 following discovery of base metals in the
area. Since that time systematic exploration and small-scale mining has occurred; this included the
construction of a concentrator treatment plant, mining facilities, substantial mining camp/township
and associated services in the 1980s.
KGL acquired the project in 2011. The project leases are owned by Jinka Minerals Limited, a 100%
owned subsidiary of KGL and the project will be operated by Jervois Operations Pty Ltd, also a 100%
owned subsidiary of KGL. KGL completed a feasibility study (FS) for the project in November 2022,
with exploration continuing throughout the subsequent development of the FSU 2025 during 2023
and 2024.
The objective of the FSU 2025 is to demonstrate viability of project operations. Development has
been targeted for the second half of this decade, to coincide with an undersupply of copper later in
the decade being forecast by independent market analysts.
KGL has prepared this FSU 2025 recognising and, where possible, mitigating the negative effects
of external factors via a lower risk mine development sequence that reduces project delivery
complexity, project capital and initial operating expenditure.
Project development is scheduled over two years, covering infrastructure and process plant
development (18 months) followed by plant commissioning and production ramp-up during the final
six months of the development schedule.
Open-cut operations are the primary ore source for the first three years of the project life. This
reduces up front mine development and mining costs, simplifies operations during plant
commissioning and reduces pre-production capital expenditure. Underground operations are
progressively scheduled to deliver ore production to sustain process plant feed as open-cut
operations decline. This mine development sequence delays higher grade copper in the
underground reserves until later in the mine life but, more importantly, results in lower project
execution complexity.
KGL RESOURCES LIMITED
Page 2
Jervois Copper Project
Feasibility Study Update
The KGL business model is based on a fully contracted operational model for both project
development and ongoing operations. KGL will maintain a lean site based organisational structure
with a contract management focus. KGL as the contract owner will maintain overall responsibility for
safety and environmental compliance and will maintain control over budget planning and quality
assurance of the copper concentrate.
KGL expects to produce the best project outcomes by engaging contractors with existing capability
and capacity to deliver in a resource constrained and low unemployment market to reduce project
execution risk.
All major operational components, such as mining, processing and camp management, will be
contracted to proven service providers with demonstrated capability and capacity for safety and
environmental management, operations and maintenance. These contracts will also include
responsibility for maintenance related activities. The intent is to engage contractors and leverage
their existing supplier relationships and draw on their internal skills capability. KGL will take an
auditing and oversight role of the selected contractors.
1.2
Key project features
The project’s key features are as follows in Table 1-2.
Table 1-2: Jervois Copper Project key technical features
Project Area
Mining
Project Element
Detail
Resource
4.40 Mt Measured @ 1.90% Cu, 32.8 g/t Ag & 0.30 g/t Au
13.24 Mt Indicated @ 1.95% Cu, 29.4 g/t Ag & 0.28 g/t Au
11.31 Mt Inferred @ 1.48% Cu, 16.4 g/t Ag & 0.14 g/t Au
Mining Areas
Open-cuts – Reward & Bellbird
Undergrounds – Rockface, Reward / Marshall, & Bellbird
Reserve
4.19 Mt Proven @ 1.79% Cu, 31.03 g/t Ag & 0.29 g/t Au
10.19 Mt Probable @ 1.76% Cu, 26.27 g/t Ag & 0.25 g/t Au
Open-Cut Mining
Conventional open-cut drill and blast, load and haul
Stripping Ratio of 11.2 waste bcm / tonne of OP ore mined
Underground Mining
Underground decline access, longhole stope mining with
selected cement rockfill, secondary access via ventilation
rises for each underground mine
14 months of development prior to ore stope production
Underground operations for 6.8 years
Life of Mine (“LOM”)
10 years (Mining)
Ore Mined
(variance from
reserves is inferred
resource category)
KGL RESOURCES LIMITED
Bellbird OP (Transition & Oxide)
487kt, Cu 2.11%
Bellbird OP (Fresh)
1,503kt, Cu 1.6%
Reward OP (Transition & Oxide)
426kt, Cu 1.98%
Reward OP (Fresh)
4,456kt, Cu 1.44%
Bellbird UG
1,380kt, Cu 1.59%
Reward UG
3,164kt, Cu 1.86%
Rockface UG
3,346kt, Cu 2.53%
Marshall UG
1,827kt, Cu 1.19%
TOTAL
16,589kt, Cu 1.77% (average)
Page 3
Jervois Copper Project
Feasibility Study Update
Project Area
Project Element
Detail
Flowsheet
Process plant nameplate capacity 2.0Mtpa ore feed
Process elements include ore crushing, grinding to 120um,
two stage froth flotation with secondary grind to 38um
Concentrate and tailing dewatering and storage
Recoveries (LOM)
92.0% Cu, 55.3% Au, 66.0% Ag (excludes transition & oxide)
Metal Produced (LOM)
983 kdmt Concentrate, Steady state 30kt Cu contained
annually
Plant Operations
10 years from first mill feed
Q1 to Q2 2027: Plant commissioning / ramp up
Q3 2027 to Q2 2035: Steady state mill feed @ 2.0Mtpa (OP)
or 1.6Mtpa (UG)
Q3 2035 to Q4 2036: Ramp down
Copper Production per
annum (pa)
Total production: 266 kt Cu, 9,442 Moz Ag, 76.1 koz Au
Average steady state production: Cu ~29.4 kt pa,
Ag ~1,005 koz pa and Au ~8.4 koz pa
Average Concentrate
Grade (dry
concentrate basis)
~27% copper in concentrate
By-products: 299g/t Ag and 2.41g/t Au
Concentrate
Production Steady
State (12% moisture in
wmt)
Average production in 2028-2035: ~111,000 dmt
Mining & Processing
Contractors used for open-cut mining, underground mining
and process plant operations
Tailings Disposal
Conventional thickened tailings
Tailings Storage
Facility
Single cell facility with water recycling to process
Staged design (wall raises) using mine waste rock
Site Access
Plenty Highway, Lucy Creek Station Road and Site Access
Road
Power
16MW Power Purchase Agreement basis
Based on a hybrid power generation facility (solar PV, wind,
battery and diesel generation)
Water
1,594MLpa of groundwater supply available from ML32277,
~20km north of the mine and ML30182, and 87MLpa from the
Jervois Dam within ML30180. Supply exceeds requirements
by ~25%.
Camp
300 room camp built & operated by contractors
Airstrip
New 100-seat-jet capable airstrip adjacent the
accommodation facility. Owned and operated by KGL.
Concentrate Transport
& Refining
Concentrate to be sold Free on Transport (FOT / ex site) to an
offtake buyer
Processing
Operations &
Maintenance
Tailings
Infrastructure
Product
KGL RESOURCES LIMITED
Page 4
Jervois Copper Project
Feasibility Study Update
1.3
Copper market forecasts
As the clean energy transition accelerates, cumulative demand for copper is expected to grow
substantially. Most nations have committed to Net-Zero Emissions targets. CO2 emissions need to
fall by about 45% from 2010 levels by 2030 to reach net zero by 2050
Wood Mackenzie analysts expect copper demand to grow by around 75% to 2050 from 30.4 Mt
(2021) to 56 Mt a year by 2050.1
Global copper demand is expected to accelerate for the period 2021-2035 to grow at 2.6% annually
or roughly 1 Mt copper demand growth per year compared with a 1.9% CAGR over the past 15
years.
Surging demand is being driven by the simultaneous adoption of copper-intensive technologies, such
as electric vehicles (EVs), renewable energy systems, grid investments, and data centres, alongside
continued economic development in emerging markets.
The FSU 2025 has adopted the December 2024 spot price of US$4.58/lb for a contemporaneous
base line which is consistent with the London Metal