KGL Resources Limited (ASX:KGL) is pleased release the company’s FY2026 Annual Report.
KGL Resources also advises the Annual General Meeting will be held on 24 November 2026.
Approved for release by the board of directors of KGL Resources Limited
FY20206 Annual Report
ANNUAL REPORT
30 June 2026
Contents
1 Corporate Directory
2 Message from the Chairman
5 CEO Operations Review
12 Reserves and Resources Table
13 Competent person’s statement
14 Tenement Holdings
16 Sustainability
17 Corporate Governance Statement
19 Financial Report
82 Additional Information
Name of Company Secretary
Kylie Anderson
Address of Registered Office
KGL Resources Limited
Level 1, 5 Gardner Close
Milton QLD 4064 Australia
07 3071 9003
Name and Address of Share Registry
MUFG Corporate Markets (AU) Limited
Tower 4
727 Collins Street
Docklands VIC 3008
Securities Exchange Listing
Quotation has been granted for the unrestricted ordinary shares
of the company on all member exchanges of the Australian
Securities Exchange.
Corporate Directory
Page 1 | KGL Resources Ltd Annual Report 2026
Message from the Chairman
Dear Shareholders,
FY2026 was a transformational year for KGL Resources Ltd (KGL), culminating in the high-grade Jervois Copper-
Silver- Gold Project (Jervois Project) becoming fully funded to production at the time of preparing this report.
Over the year, KGL materially advanced the Jervois Project. The Company secured a US$300 million cornerstone
precious metals purchase agreement (PMPA) for silver and gold with Wheaton Precious Metals International
Ltd (Wheaton) and completed a A$300 million equity raising post balance date. Together with existing cash,
these provide approximately A$689 million of aggregate funding that provides a prudent liquidity buffer to
complete project construction and commissioning, and to extend the operational life by targeting high potential
exploration, adjacent to planned mining areas.
KGL’s business plan has attracted strong support from existing shareholders as well as new domestic and
international institutional investors and funds. Together with Wheaton’s commitment, we view this support as
an endorsement of the quality of the high-grade Jervois Project and the KGL team’s approach.
During the financial year, the copper price increased by 24%, from about US$11,000 to about US$13,600 per
tonne between July 2025 and June 2026. This upward trend has continued into the 2026/2027 financial
year, supported by market analysts’ views suggesting a target of some US$15,000 per metric tonne1
.
Importantly, the funding structure does not include conventional project debt and leaves KGL’s copper
offtake fully exposed to movements in the copper price.
The Baseline Economic Model (BEM) announced in April 2026 confirmed the strength of the Jervois
development case, with a post-tax NPV of approximately A$839 million (8% discount rate), a post-tax IRR of
31% and an estimated C1 cost of US$1.65 per pound of copper.
The value of Jervois is highly leveraged to the LME copper price which has increased from the BEM modelled
price of US$13,360 per metric tonne to circa US$14,400 per metric tonne in less than 6 months since the BEM
announcement. The project valuation sensitivity analysis reported in the BEM showed that the value of the
project (NPV) increases above the A$839 million valuation by A$140 million for each US$1,000 increase in the
copper price per metric tonne.
During the year, KGL advanced process-plant engineering, contracting, procurement, long-lead equipment
procurement, the open-pit mining contract process and early site works. The Integrated Owner’s Team was
strengthened and a separate Project Steering Committee, reporting to the Board, was formed to provide
additional oversight and expertise to support project delivery.
With funding secured and the development case defined, KGL’s focus has shifted decisively from financing
and construction readiness to preparing for project execution, with first copper concentrate production
targeted in 2028.
During FY2026, KGL strengthened its leadership and governance capability with the appointment of
Sam Strohmayr as Chief Executive Officer and Lindi Deguara as an Independent Non-Executive Director.
Subsequent to year end, Gerard Hutchinson joined the Board as an Independent Non-Executive Director,
adding further finance, governance and executive experience.
1
UBS Global Research, copper price forecast update, reported in “UBS raises copper price target on supply deficit outlook”, Investing.com,
27 February 2026, https://www.investing.com/news/commodities-news/ubs-raises-copper-price-target-on-supply-deficit-outlook-93CH-4530640
Page 2 | KGL Resources Ltd Annual Report 2026
Jeff Gerard
Chairman
Brisbane
29 September 2026
The 2026 financial year has seen an exemplary safety and environmental management record with no
incidents. The company also completed a detailed self-assessment of its ESG systems and processes
against the Consolidated Mining Standard Initiative (CMSI) international standard that has demonstrated
significant compliance and effectiveness, even at this early stage of development.
Ongoing interactions with the NT Government, Central Lands Council, local Bonya Community, local
landholders, local service providers, contractors and consultants have continued to maintain strong and
positive relationships.
On behalf of the Board, I thank both our long term and new shareholders, employees, contractors, advisers,
and stakeholders for their ongoing support during an important year for KGL. Since the financial year end
KGL has been included in the S&P/ASX All Ordinaries index, effective 21 September 2026.
Our priorities are clear: achieve Final Investment Decision (FID), safely progress mobilisation and
construction, ensure effective environmental and cultural heritage management, disciplined project
execution and capital management. In addition, we will be advancing a fully funded exploration program
whilst continuing to progress Jervois towards first copper concentrate production in 2028.
The year ahead is about converting FY2026’s platform into the safe, disciplined development of Jervois as
Australia’s next significant ASX-listed pure-play copper producer.
Page 3 | KGL Resources Ltd Annual Report 2026
2
Post end of financial year.
MILESTONES AT A GLANCE
2025 2026
JUL
Integrated
3D inversion
targets
identified
OCT
A$11m
placement
completed
NOV
Lindi
Deguara
appointed
to Board
DEC / JAN
Sam
Strohmayr
appointed /
commenced
as CEO
2 APR
US$300m
Wheaton
PMPA
executed
24 APR
Updated
BEM
released
18 JUN
First
US$16m
Wheaton
tranche
29 JUN
A$180m
Placement
book build
completed
24 JUL
A$120m
Entitlement
Offer
completed
FY2026
A TRANSFORMATIONAL YEAR
High-Grade Jervois Project — Fully Funded2
to Production
FY2026 marked a defining transition for KGL – from an
exploration and development-stage company to a fully funded
copper developer advancing the high-grade Jervois Project
toward production.
The transformation was built through key milestones that
deepened our understanding of the Jervois mineral system,
strengthened institutional and leadership capability, advanced
the development case and secured the funding required to
deliver Jervois into production.
FY2026 KEY OUTCOMES
3D INVERSION
POTENTIALLY LARGER
& DEEPER SYSTEM
Potentially larger
and deeper mineral
system identified through
integrated 3D inversion
INSTITUTIONAL
SUPPORT
Strong institutional
support for placement
and strengthening
shareholder base
BOARD + CEO
LEADERSHIP
STRENGTHENED
Board capability enhanced
and Sam Strohmayr
appointed CEO to lead KGL
into project execution
A$839m / 31%
UPDATED
DEVELOPMENT CASE
BEM confirms compelling
economics with significant
leverage to higher
copper prices
~A$689m
FUNDING PACKAGE2
Aggregate funding
package established
with no project debt
A LARGER AND DEEPER
MINERAL SYSTEM
Integrated 3D inversion
identifies new priority targets
FULLY FUNDED2
TO PRODUCTION
Funding secured to advance
Jervois through production
FUNDED GROWTH BEYOND
THE CURRENT MINE PLAN
Exploration program to test
resource growth and extend
FUNDING SECURED
US$300m
WHEATON PMPA
US$300 million
cornerstone development
funding secured
A$300m
EQUITY RAISING2
A$300 million Equity
Raising completed to fully
fund development
NO PROJECT
DEBT
Debt-free financing
structure preserves
balance sheet flexibility
~A$20m
FUNDED EXPLORATION
Exploration and drilling
program funded to test growth
and extension potential
No project debt Copper offtake unencumbered Funding through construction, commissioning and into production
Page 4 | KGL Resources Ltd Annual Report 2026
I was pleased to join KGL as Chief Executive Officer in January 2026 at an important point in the Company’s
transition from project development to execution.
Since joining, my focus has been on building the capability required to move KGL from exploration to project
development and execution, and on advancing the work needed to take the Jervois Project through to FID,
construction and ultimately into operations.
FY2026 marked an important transition as KGL progressed Jervois from development planning and readiness
towards execution.
During the year, KGL advanced project enabling and readiness activities, completed the BEM, strengthened its
project-delivery capability and materially advanced its understanding of the broader Jervois mineral system.
With funding secured, our focus is now firmly on project execution.
THE JERVOIS DEVELOPMENT CASE
During FY2026, KGL completed further optimisation of the Jervois Project development plan, culminating in the release
of the updated BEM in April 2026. The BEM incorporated further open-pit optimisation, improved metallurgical recovery
and updated capital and operating cost assumptions.
Construction capital increased from approximately A$362 million in FSU25 to A$439 million in the BEM, reflecting scope
and risk-mitigation changes incorporated into the development plan.
The BEM confirmed a post-tax NPV of A$839 million at an 8% discount rate, a post-tax IRR of 31% and an estimated
C1 cost of US$1.65/lb, providing a strong economic foundation for development of Jervois.
The BEM is based on a production plan with initial ore supply from the Bellbird and Reward open pits before
progressively transitioning to underground mining at Bellbird, Reward, Rockface and Marshall. The current development
case is based on an initial 10-year mine life, with average copper production of approximately 30kt per annum.
CEO Operations Review
ASSUMPTION UNIT BEM
Mine life Years 10
LOM EBITDA A$m 3,226
LOM FCF (after tax) A$m 1,791
Concentrate produced (LOM) kdmt 1,070
PRODUCTION
Avg. Copper LOM ktpa 30
Avg. Silver Mozpa 1.1
Avg. Gold kozpa 9.3
UNIT COSTS (NET OF BY-PRODUCT)
C1 Cost US$/Ib 1.65
AISC (incl. 100% of underground capital) US$/Ib 2.51
UPFRONT CAPITAL COSTS
Project construction capital A$m 439
Mining & stockpiling (incl. ~4 months of sulphide stockpiles) A$m 145
Peak funding requirement A$m 584
ECONOMIC RETURN
Post-tax NPV8 A$m 839
Post-tax IRR % 31
Page 5 | KGL Resources Ltd Annual Report 2026
FID and commencement of the principal construction program remain targeted for H2 CY2026. The development
schedule provides for approximately 18 months of construction, followed by commissioning and ramp-up, with first copper
concentrate targeted in H1 CY2028 and full processing capacity expected during H2 CY2028.
PROJECT DEVELOPMENT AND DELIVERY
During FY2026, KGL continued to build the internal management, engineering, procurement and operational
capability required to oversee development and to prepare for construction and operations. This included
strengthening project controls, contractor management, cost and schedule oversight, safety, commissioning and
operational readiness, supported by specialist contractors and advisers.
Work also progressed across engineering, procurement, contracting, long-lead equipment planning and project
readiness, advancing Jervois towards its next major decision point.
With project development activities advancing, KGL is progressing Jervois towards FID and commencement of the
principal construction program.
CEO OPERATIONS REVIEW (CONTINUED)
WORKSTREAM 2026 2027 H1 2028 H2 2028 2029+
PROJECT DEVELOPMENT
ACTIVITIES
MAJOR CONTRACTS / DESIGN
& LONG-LEAD PROCUREMENT
PRINCIPAL CONSTRUCTION
PROGRAM
OPEN-PIT MINING
SULPHIDE ORE STOCKPILING
PLANT COMMISSIONING /
FIRST SULPHIDE MILL FEED
FULL PROCESSING CAPACITY
UNDERGROUND
DEVELOPMENT
3
Post end of financial year.
A$839m
POST-TAX
NPV8
31%
POST-TAX
IRR
US$1.65/lb
C1
COST
US$10,200/t
CAPITAL
INTENSITY
US$6.06/lb
BASE-CASE
COPPER PRICE
KEY ECONOMICS
~A$689m
AGGREGATE
FUNDING
US$300m
WHEATON
PMPA
A$300m
EQUITY
RAISING
~A$70m
LIQUIDITY
BUFFER
~A$20m
FUNDED
EXPLORATION
PROGRAM
FUNDING
3
Continuing activities
to decision
Contracts awarded,
design finalised and
long-lead items secured
~4 months sulphide
ore inventory ahead
of commissioning
Plant commissioning
From 2029
Principal construction
commences after FID
FID
H2 CY2026
Commences
mid-2027
First sulphide
mill feed
Page 6 | KGL Resources Ltd Annual Report 2026
EXPLORATION AND RESOURCE GROWTH
Alongside development of the current mine plan, KGL materially advanced its understanding of the broader Jervois
mineral system through an Integrated 3D Inversion Modelling program across Jervois and Unca Creek, combining more
than a decade of drilling knowledge with gravity, magnetic, magnetotelluric and petrophysics datasets.
The integrated modelling improved targeting across the broader mineral system, increased confidence in previously
recognised anomalies and identified several new priority exploration targets.
The modelling provided what KGL considers its strongest geophysical evidence to date of a larger and deeper mineral
system at Jervois. The next phase is focused on testing these opportunities through further geophysics work and drilling.
Approximately A$20 million has been allocated to exploration and drilling across Jervois and Unca Creek, targeting
near-mine resource growth, mine-life extension and potential new mining areas. Subsequent to year end, KGL
commenced preparations for drilling several high-priority targets and further geophysics surveying across the Jervois
and Unca Creek tenements.
The current BEM does not assign value to future exploration discoveries or potential mine-life extension, meaning
successful exploration represents potential upside beyond the 10-year mine life case.
LOOKING AHEAD
Equipped with achievements to-date, our priorities for FY2027 are clear: complete the remaining development
contracts, achieve FID, commence construction and maintain disciplined execution across safety, schedule, cost and
quality as Jervois progresses towards first copper concentrate in 2028.
FULLY FUNDED TO
PRODUCTION
Funding designed to
support development,
construction, commissioning
and ramp-up.
NO CONVENTIONAL
PROJECT DEBT
Funding structure
avoids conventional
project-debt
financing.
COPPER REMAINS
UNENCUMBERED
KGL retains exposure
to copper revenues
and flexibility over
future offtake.
LIQUIDITY THROUGH
RAMP-UP
Approximately
A$70 million
working capital and
liquidity provision.
GROWTH
FUNDED
Approximately
A$20 million
allocated to geophysics,
drilling and analysis.
The focus for the year ahead is safe delivery as we move Jervois from project development into construction and
towards operations.
Sam Strohmayr
Chief Executive Officer
CEO OPERATIONS REVIEW (CONTINUED)
Page 7 | KGL Resources Ltd Annual Report 2026
EXPLORATION
Integrating More Than a Decade of Geological Knowledge to Guide the Next Phase of Growth
While FY2026 established the funding and development pathway for the current 10-year Jervois mine plan, it also
materially advanced KGL’s understanding of the broader mineral system and the potential for future resource growth
beyond the current development case.
A Major Technical Achievement
During FY2026, KGL announced the results of a major Integrated 3D Inversion Modelling program undertaken by
Viridien’s Multiphysics team across the Jervois and Unca Creek exploration leases. The work incorporated considerable
geological knowledge built up by KGL over more than 10 years of drilling together with extensive gravity, magnetic,
magnetotelluric and petrophysics datasets.
Historically, many of these datasets had been analysed independently. Advances in computing capability, geoscientific
expertise and the enriched geological dataset generated through drilling and core analysis enabled the different data
streams to be analysed together through joint inversion modelling.
An important precursor was the 2024 structural review undertaken by Dr Warwick Crowe. That work refined KGL’s
understanding of the controls on mineralisation at Jervois, including the interpretation that the crustal-scale Jervois Fault
may have acted as a major pathway for mineralising fluids feeding subsidiary structures associated with the J-Fold. It
also highlighted the importance of subsidiary structural systems, contrasting lithologies and reactivated shear zones in
exploration targeting.
Improved Resolution and Targeting Precision
The integrated approach combined gravity, magnetotelluric, magnetic and petrophysical drilling data to provide improved
subsurface resolution and targeting precision compared with single-parameter inversion approaches. The resulting
models further delineated known zones of mineralisation, demonstrated strong correlation with existing geological data,
increased confidence in previously recognised anomalies and identified several new priority exploration targets.
A Potentially Larger and Deeper Mineral System
Importantly, the modelling identified prominent deep-seated low-resistivity features beneath the central J-Fold and
Bellbird–Rockface trend. Apparent-resistivity mapping identified features extending to greater than 5 kilometres depth,
while the integrated model identified prominent conductive zones at approximately 3 kilometres depth.
These responses are interpreted as potentially associated with major structurally controlled features, alteration, fluid
pathways or mineralising systems associated with the J-Fold and deeper Jervois Fault architecture. They should not be
interpreted as demonstrated mineralisation or Mineral Resources.
KGL concluded that the study provides its strongest geophysical evidence to date that Jervois hosts a significantly larger
and deeper mineral system than previously identified. Priority target corridors include the central J-Fold, a trend south of
Bellbird, a parallel trend south of Rockface and the continuation of Reward South/Krak Ridge.
Unlocking Growth Potential for Beyond 10 years
The Integrated 3D Inversion Model provides an ongoing exploration framework rather than a static interpretation.
New geophysical, drilling and geological information can be progressively incorporated to improve resolution and
refine subsequent targeting.
Approximately A$20 million has been allocated to a staged exploration and drilling program targeting near-mine resource
growth, mine-life extension and potential new mining areas across Jervois and Unca Creek. The program will incorporate
additional MT, DHEM and other geophysical work together with targeted drilling and core analysis. Subsequent to year
end, KGL commenced preparations for exploratory drilling of several high-priority targets and for further MT surveying
across the Jervois and Unca Creek tenements.
The current BEM does not assign value to potential mine-life extension or future exploration discoveries. Successful
exploration therefore represents potential upside beyond the funded 10-year development case. Exploration targets and
geophysics anomalies are not Mineral Resources or Ore Reserves and there can be no certainty that exploration will result
in additional resources, reserves or mine life.
CEO OPERATIONS REVIEW (CONTINUED)
Page 8 | KGL Resources Ltd Annual Report 2026
Figure 1. Horizontal slice of the joint magnetic imagery guided MT and gravity inversion model at 0.0 mRL (approximately 350 m below
surface). Resistivity is displayed using the colour scale, while inverted density is represented by contour lines. Purple triangles denote
MT sounding stations, and black lines indicate structural interpretations derived from magnetic data. Several anomalies have been
identified within Jervois Tenement (EL25429): Area 1 is positioned directly over the F3/J-Fold axis, Area 2 defines a distinct parallel trend
to Bellbird, Area 3 forms an offset parallel trend to Rockface, and Area 4 aligns closely with the Reward South trend.
Figure 2. Cross section at 7492418.00mN looking north highlighting resistivity of Area 1 (J-fold centre).
Page 9 | KGL Resources Ltd Annual Report 2026
COPPER MARKET
Structural trends support the long-term copper outlook
FY2026 saw strong gains in copper, gold and silver prices, providing a supportive commodity backdrop as KGL advanced
the Jervois Project towards execution.
CEO OPERATIONS REVIEW (CONTINUED)
Page 10 | KGL Resources Ltd Annual Report 2026
Copper Demand — Structural Growth
S&P Global forecasts global copper demand to increase by approximately 50%, from 28 million tonnes in 2025 to
42 million tonnes by 2040. Traditional copper demand continues to grow with population, urbanisation, industrialisation
and rising living standards, while demand from electrification, electricity infrastructure and emerging technologies is
accelerating growth.
Energy transition and electricity infrastructure are forecast to be major sources of incremental demand, including
renewable generation, transmission and distribution, battery storage and electric vehicles.
The expansion of electricity networks is an important part of this growth. S&P Global estimates more than US$7.5 trillion
of global transmission and distribution investment through 2040.
EV-related copper demand is forecast to rise from 2.6 million tonnes in 2025 to 6.3 million tonnes by 2040, while
data-centre-related copper demand is forecast to increase from approximately 1.1 million tonnes to 2.5 million tonnes.
50% total demand growth | >US$7.5tn grid investment | 2.6 → 6.3 Mt EV demand
Copper supply — tightening and increasingly strategic
Near-term market conditions are already reflecting the longer-term supply challenge. UBS forecasts a refined copper
deficit of approximately 520,000 tonnes in 2026, against a backdrop of continued constraints on new and existing supply.
Declining grades, ageing mines, greater mining depth and complexity, long development timelines and rising capital
requirements are making replacement supply progressively more difficult and expensive. S&P Global forecasts primary
mined supply peaking around 2030 without sufficient new development and expansion, contributing to a potential annual
shortfall of approximately 10 million tonnes by 2040.
Competition to secure and diversify copper supply chains is also intensifying. Copper recognised as a critical or strategic
material by the United States, European Union and Australia, reflecting its importance to electricity infrastructure,
advanced manufacturing, digital technologies and defence.
Jervois — New Supply into a Tightening Market
First copper concentrate from Jervois is targeted in 2028, positioning KGL to introduce new Australian copper supply into
a market in which deficits are forecast to deepen and new mine development is becoming increasingly capital intensive.
The BEM indicates Jervois capital intensity of approximately US$10,200/t of annual copper production capacity, compared
with an average of approximately US$22,400/t across 26 global copper projects assessed by Simon et al. (2026).
Jervois’ high-grade resource, relatively low capital intensity and projected operating margins position the Project well as
the industry seeks to bring additional copper supply to market.
2028 first copper | ~US$10,200/t Jervois capital intensity | >US$22,400/t peer project average
Precious Metals — Additional Support
Gold and silver also provide meaningful by-product credits to Jervois, providing additional support to the
Project’s economics.
Sources: S&P Global, Copper in the Age of AI, January 2026; S&P Global Ratings; UBS CIO; Cochilco; Codelco; Simon et al., 2026; KGL June 2026 Quarterly
Activities Report.
Page 11 | KGL Resources Ltd Annual Report 2026
Reserves and Resources Table
RESOURCE MATERIAL GRADE METAL
Area Category Mt
Copper
(%)
Silver
(g/t)
Gold
(g/t)
Copper
(kt)
Silver
(Moz)
Gold
(koz)
Open Cut Potential
> 0.5% Cu
Reward
Measured 2.57 1.95 48.2 0.43 50.0 4.0 35.4
Indicated 1.02 1.39 37.4 0.23 14.3 1.2 7.6
Inferred 0.61 0.95 10.7 0.08 5.8 0.2 1.5
Bellbird
Measured 1.23 2.53 15.1 0.14 31.2 0.6 5.6
Indicated 1.26 1.45 9.1 0.17 18.2 0.4 6.8
Inferred 1.02 1.24 10.6 0.12 12.7 0.3 4.0
Sub Total 7.72 1.71 27.2 0.25 132.1 6.7 60.9
Underground
Potential
> 0.8% Cu
Reward
Indicated 6.22 1.87 38.4 0.38 116 7.67 75.5
Inferred 4.71 1.35 18.6 0.17 63.6 2.82 25.5
Bellbird
Indicated 0.35 2.26 19.0 0.14 8.0 0.22 1.6
Inferred 3.20 1.95 12.1 0.10 62.4 1.24 10.4
Rockface
Indicated 3.94 2.81 24.5 0.26 110.9 3.10 32.71
Inferred 1.32 1.55 13.7 0.19 20.42 0.58 8.02
Sub Total 19.74 1.93 24.6 0.24 381.3 15.63 153.7
TOTAL 27.45 1.87 25.3 0.24 513.4 22.37 214.5
Refer to ASX announcement on 25 November 2024.
* Cut-off grades: 0.5% Cu above 200 mRL (~150 m below surface) and 0.8% Cu below 200 mRL.
GRADE METAL
RESERVES Mt
CuEq
(%)
Cu
(%)
Au
(g/t)
Ag
(g/t)
Cu
(kt)
Au
(koz)
Ag
(Moz)
Reward Open Pit
Proven 2.68 2.19 1.71 0.39 41.96 45.7 33.6 3.6
Probable 2.2 1.54 1.19 0.22 36.3 26.1 15.6 2.6
Bellbird Open Pit
Proven 1.51 2.07 1.94 0.11 11.59 29.2 5.3 0.6
Probable 0.48 1.1 1.04 0.06 5.55 5 0.9 0.1
Rockface Underground
Proven - - - - - - - -
Probable 2.96 2.74 2.55 0.18 16.58 75.4 17.0 1.6
Bellbird Underground
Proven - - - - - - - -
Probable 0.37 1.77 1.65 0.08 13.23 6.0 1.0 0.2
Reward Underground
Proven - - - - - - - -
Probable 2.48 2.28 1.88 0.49 25.77 46.7 38.8 2.1
Marshall Underground
Proven - - - - - - - -
Probable 1.71 1.51 1.16 0.19 39.52 19.8 10.2 2.2
Sub-total 1.71 1.51 1.16 0.19 39.52 19.8 10.2 2.2
Total Proven 4.19 2.15 1.79 0.29 31.03 74.9 39 4.2
Total Probable 10.19 2.05 1.76 0.25 26.27 179 83.4 8.6
TOTAL RESERVE 14.38 2.08 1.77 0.26 27.66 254 122.4 12.8
Refer to ASX announcement on 10 February 2025.
* Quantities and grades in the above table may not add exactly due to rounding or weighting. The ore reserves reported are contained within the mineral resources.
Page 12 | KGL Resources Ltd Annual Report 2026
Competent person’s statement
The information in this report that relates to a Production Target and the forecast financial information derived from
the production was first released to the market on 24 April 2026. KGL confirms that all the material assumptions
underpinning the production target and forecast financial information derived from the production target continue to
apply and have not materially changed.
The information relating to 3D Inversion results was originally reported on 30 July 2025. The Company confirms
it is not aware of any new information or data that materially affects the information included in the original market
announcement and that all material assumptions and technical parameters underpinning the estimates in the relevant
market announcement continue to apply and have not materially changed.
The information in this report that relates to the Jervois Mineral Resources Estimates was first released to the market
on 25 November 2024 and prepared in accordance with JORC 2012. The company confirms that it is not aware of any
new information or data that materially affects the information included in the original market announcement and that
all material assumptions and technical parameters underpinning the estimates in the relevant market announcement
continue to apply and have not materially changed. The company confirms that the form and context in which the
Competent Person’s findings are presented have not been materially modified from the original market announcement.
The information in this report that relates to the Jervois Ore Reserves Estimate was first released to the market on
10 February 2025 and prepared in accordance with JORC 2012. The company confirms that it is not aware of any
new information or data that materially affects the information included in the original market announcement and that
all material assumptions and technical parameters underpinning the estimates in the relevant market announcement
continue to apply and have not materially changed. The company confirms that the form and context in which the
Competent Person’s findings are presented have not been materially modified from the original market announcement.
Page 13 | KGL Resources Ltd Annual Report 2026
TENEMENT
NUMBER
PROJECT
BENEFICIAL
HOLDING
EXPIRY
DATE
ML 30180 Jervois Project, Northern Territory 100% 27/01/2034
ML 30182 Jervois Project, Northern Territory 100% 25/03/2034
ML 30829 Jervois Project, Northern Territory 100% 17/08/2032
ML 32277 Jervois Project, Northern Territory 100% 17/08/2032
EL 25429 Jervois Project, Northern Territory 100% 01/02/2027
EL28082 Unca Creek, Northern Territory 100% 29/12/2027
EL 30242 Mt Cornish, Northern Territory 100% 25/11/2027
EL 28340 Yambah, Northern Territory 100% 03/07/2027
Tenement Holdings
The Company’s current tenement holdings cover over 252km2
of Jervois Exploration Leases, 37.9km2
of Jervois
Exploration Licences and 72.7km2
of Unca Creek Exploration Licences.
Page 14 | KGL Resources Ltd Annual Report 2026
JERVOIS PROJECT TENEMENTS MAP
Page 15 | KGL Resources Ltd Annual Report 2026
Sustainability
Environmental, social and governance (ESG) reporting
and Indigenous relations continued to be key focus areas
for KGL during the reporting period.
The Company further strengthened its commitment
to health and safety through ongoing monitoring,
continuous improve