Update on PFS optimisation of the Jervois Copper Project
Released
Released
Announcement PDF
www.kglresources.com.au
20 April 2015
Update on pre-feasibility study optimisation of the Jervois
Copper Project
Summary
The pre-feasibility study of the Jervois Copper Project in the Northern Territory completed in
December 2014 found Jervois to be a viable project with strong upside potential from
additional drilling and metallurgical work. KGL Resources Limited (KGL or the Company)
decided to undertake an additional work program to improve the economics.
Work to date is summarised below:
an updated Mineral Resource estimate that is expected to be announced in July
2015
promising increases in recoveries of copper and silver
processing improvements to include transitional ores and lead-zinc ore
possible savings to capital expenditure and operating costs
expected reductions in mining costs from the 2014 estimates.
Background
In September 2014, the Company announced the fourth increased Resource estimate in
three years of KGL’s ownership of Jervois, comprising 25.3 million tonnes @ 1.1% copper
and 22.1 g/t silver, containing 280,000 tonnes copper and 18 million ounces silver with an
additional exploration target of 50,000 to 150,000 tonnes copper and 2 to 7 million ounces
silver*, together with 120,000 tonnes lead/zinc and 113,000 ounces gold.
*The potential quantity and grade of the Exploration Potential is conceptual in nature and
there has been insufficient exploration to define a Mineral Resource. It is uncertain if further
exploration will result in the determination of a Mineral Resource.
Jervois was shown to be technically and commercially feasible, with annual production in
concentrate over an initial seven year mine life of approximately 21,000 tonnes copper and 1
million ounces silver plus gold, lead and zinc. Initial capital expenditure was estimated at
A$189M including A$22M in contingency, and C1 cash costs estimated at US$1.51/lb
copper (after by-product credits and using an exchange rate of A$/US$0.845 and silver price
of US$20/oz.
With continuing good drill results pointing to a larger, more valuable asset, the Company
decided to undertake an additional work program, to improve the economic parameters, and
targeting $100M to $200M of additional free cash flow over the life of the project.
www.kglresources.com.au
Current status
The PFS study optimisation work comprises
Additional resource drilling
Metallurgical work and flow sheet optimisation
Geotechnical review
Review of mining and other operating costs
Resource Drilling
A resource extension, RC drilling program commenced in February at the Bellbird, MarshallReward and Green Parrot Resources. Particular emphasis was placed on targeting poorly
drilled portions of these resources that have potential for high-grade mineralisation and are
within or immediately adjacent to the proposed open pits or close to planned underground
mine development.
This program of 9,400m is now completed and a further 2,000m of drilling has commenced
to bring recently discovered near surface copper mineralisation at Sykes, Johannsen and
East Reward into the next resource update. Two additional holes beneath the Green Parrot
resource are also planned as part of this extended program. It is anticipated that all of the
planned drilling will be completed by the end of the week. Assay results are anticipated
periodically over the next four weeks. These results will be used to complete an updated
Resource estimate that is due for completion in July 2015.
Metallurgical test work and flow sheet optimisation
Outcomes from previous studies suggest that by modifying the process plant it is possible to
treat ore extracted from the oxide/sulphide transitional zones, and to allow treatment of ore
extracted from the high grade lead-zinc zones which exist within the same deposits at
Jervois. To prove this, KGL engaged Minelogix to manage a test work program at ALS
Laboratories. The program is designed to gain a better understanding of the wider range of
ore types and to define the optimal approach for extracting copper, lead and zinc as well as
the associated precious metals in the ore.
Results so far have highlighted:
Power savings due to lower work indices for copper ores (softer ore)
Confirmation of flowsheet conditions established for copper sulphide ores in the earlier
work
Improved confidence in metallurgical response with respect to copper sulphide and
transitional ores resulting in increased copper and silver recoveries
Increased throughput in the treatment of transitional ore in the initial stages of operation
Substantial reduction in sustaining capital requirements.
Grinding
The grinding circuit was redesigned to treat a wider range of ores including sulphide/
transitional ores and lead-zinc ores. The grinding circuit was changed to a SAG and Ball
(SAB) combination rather than the previous Single Stage SAG combination. The new circuit
is superior from an operational perspective. It will improve the ability to control mill capacity
and enable the grind size to be changed as required for the range of ores in the deposit.
The overall installed power requirement was reduced to 5MW (SAB) from the previous 6MW
single stage SAG circuit due to the ore being softer than previous assumptions.
www.kglresources.com.au
Flotation
The transitional ore is softer than the sulphide ore and can be treated at increased rates in
the initial stages. This ore contains a higher secondary copper component and is able to
produce a higher grade concentrate than the sulphide copper ores. Transitional ore can be
treated with minor modifications to the sulphide flotation circuit established in the previous
study.
The concentrator design for treating both sulphide and transitional copper ore can also be
used to treat the copper-lead-zinc ore. For this ore, copper is recovered separately using
the existing copper circuit while a small regrind mill, cleaner flotation circuit and concentrate
filter are the only additional requirements to recover a lead-silver-zinc concentrate.
The metallurgical outcomes to date are encouraging and demonstrate the ability to improve
capital intensity, by reducing plant complexity and thereby reducing sustaining capital over
the life of mine. Furthermore, the process plant flowsheet utilises proven industry standard
technologies.
Test work is still underway, with 130 flotation tests having been completed to date. Of that,
60 tests were completed in March and 40 tests are scheduled for April with the program to
conclude in early May. Locked cycle confirmatory test work will be completed in late April
ahead of schedule.
Geotechnical review
The 1,200m of geotechnical diamond drilling in to the planned pit walls has been completed.
Material property test work is being carried out by WASM rock property test laboratory, and
managed by geotechnical engineers Peter O’Bryan & Associates. During March, cores from
geotechnical investigation boreholes were inspected, reviewed and samples collected for
material properties selection. A final report on the geotechnical assessment is due at the end
of April.
The aim of this work is to increase the pit slopes for the planned open cut pits. If the pit
slopes can be made steeper, then the quantity of waste to be mined will be reduced.
Review of Mining Costs
An engineering consultant will provide current mining costs through a Request for Quotation
(RFQ) process that is currently in progress.
Below are key general observations when comparing the recent 2015 RFQ submissions of
mining costs to the costs used in the 2014 study:
General load and haul unit rate cost for surface mining have decreased significantly
Site establishment, mobilisation and demobilisation have decreased significantly
The underground unit rate costs appear to have decreased moderately.
KGL is working with logistics providers to leverage their scale and expertise to reduce the
project’s operating costs. The fall in the price of diesel will also reduce operating costs
related to transport and mining.
Mining PFS Revision work is due to commence in July 2015. This will utilise an updated
dataset including mining rates, block models and operational costs. This will include PFS
level engineering required to attain optimised open pit and underground mine designs
including life-of-mine scheduling. The information from the above studies will then be used to
prepare a revised financial model for the Jervois project.
www.kglresources.com.au
For further information contact:
Mr Simon Milroy
Managing Director
Phone: (07) 3071 9003
About KGL Resources
KGL Resources Limited is an Australian mineral exploration company focussed on increasing the high
grade Resource at the Jervois Copper-Silver-Gold Project in the Northern Territory and developing it
into a multi-metal mine.
JORC Compliance Statement
The Jervois Resources information was first released to the market on 15 September 2014 and complies with JORC 2012. The
company confirms that it is not aware of any new information or data that materially affects the information included in the
original market announcement and that all material assumptions and technical parameters underpinning the estimates in the
relevant market announcement continue to apply and have not materially changed. The company confirms that the form and
context in which the Competent Person’s findings are presented have not been materially modified from the original market
announcement.’
The Jervois Pre-Feasibility Results were first released to the market on 8 December 2014 and complies with JORC 2012. The
company confirms that, apart from what is stated in this announcememt, it is not aware of any new information or data that
materially affects the information included in the original market announcement and that all material assumptions and technical
parameters underpinning the estimates in the relevant market announcement continue to apply and have not materially
changed.