Chairman's Address to Shareholders
Released
Released
Announcement PDF
www.kglresources.com.au
29 May 2015
KGL Resources (ASX:KGL) releases the Chairman’s and Managing Director’s addresses to be given at
today’s Annual General Meeting.
For further information contact:
Mr Simon Milroy
Managing Director
Phone: (07) 3071 9003
About KGL Resources
KGL Resources Limited is an Australian mineral exploration company focussed on increasing the high
grade Resource at the Jervois Copper‐Silver‐Gold Project in the Northern Territory and developing it
into a multi‐metal mine.
KGL Resources Limited ACN 082 658 080
Level 7, 167 Eagle Street, Brisbane QLD 4000 Australia
www.kglresources.com.au
Phone: (07) 3071 9003
Fax :
(07) 3071 9008
Email: info@kglresources.com.au
2015 AGM Chairman’s Address
Ladies and gentlemen, the last 12 months has been one of significant achievement
for KGL’s Jervois project in the Northern Territory, despite volatile global markets
and an uncertain commodity outlook.
At the last AGM we reported that we were well advanced with the Pre-Feasibility
Study for Jervois. Let me remind you that we had embarked on the PFS in early
2014 following completion of an encouraging initial Scoping Study. That Study had
suggested that the Project could produce around 20,000 tonnes of copper in a
copper/silver concentrate or equivalent per year, and commence with a modest
open cut mining operation followed by a move to underground workings.
Whilst the primary product would be a copper sulphide concentrate, after a few
years of operation the process plant would be modified to also produce lead and
zinc concentrates.
As part of the PFS we undertook an extended drilling program to upgrade and
increase the Project’s resource base as well as an extensive metallurgical test
program together with geotechnical studies and plant design
Today I am pleased to be able to say that in just about every aspect of the PFS
that we commenced 17 months ago, we have exceeded our goals and expectations.
In particular:
• The drilling program up until the end of June 2014, when we began the
revised calculation of the Project’s resources base, was more successful than
we had expected. The new resource estimate, announced last September,
increased copper resources by 64% to 280,00t contained copper, silver
resources by 61% to 18 million ounces, lead resources by 225% to 84,000
contained lead and zinc by 63% to 36,000 tonnes contained zinc.
• Downhole EM surveys identified potential additional mineralisation at depth.
The Project’s Exploration Target Range was increased to an additional 50150,000 tonnes of contained copper tonnes further enhancing the Projects
potential mine life.
• The metallurgical test program was also very successful in three areas:
1.The transition material responded so well to the test work that we
were able to abandon the concept of a heap leach operation and
include that material in plant feed;
2.Projected copper recoveries of primary ore material exceeded our
expectations; and
3.Probably the major breakthrough, was realising that and the Project
would be able to produce a marketable lead/zinc bulk concentrate
without the need for a separate mill circuit.
The impact of all of these developments was, that by late November last year,
when the initial PFS work was completed we concluded that the project was viable
and there were no “show stoppers”. Indeed, it was clear that because of the
positive exploration and metallurgical results a rethink was required.
• the scheduling of the proposed mining development needed to include much
larger open cut mines;
• the design of the processing plant circuit could be simplified to include the
ability to produce a mixed concentrate from day one, but not through a
separate circuit; and
• a further drilling program would be needed to upgrade the resource base by
following up newly discovered extensions to mineralisation.
So last December, just prior to the end of our FY, Management and the Board
decided that the best way forward would be for us to extend the PFS to
incorporate the new information and revise the Project development schedule.
Simon will tell you later, in more detail, what we have been and are doing, but
essentially that is where we are today.
We expect that a further upgraded estimate of the Project’s resource base will be
completed in July 2015. This will be fed into a revised mining and processing
schedule and along with updated capital and operating cost estimates, the latest
material and construction costs and current exchange rates, we anticipate that the
final results of all of this work will be available in the fourth quarter of this year.
By any measure we believe we have had a very successful year. We have managed
to complete all of this work and will be able to deliver the revised PFS later this
year with the funds we currently have available.
Of course, once we have completed this revised PFS, we will have to decide what
our next steps will be and how indeed we are going to fund them.
And that, quite neatly brings me to the subject of the global economy and world
commodity prices.
Whereas internally, we have been extremely pleased with project developments,
the same cannot be said of the global marketplace in which we operate.
Slowing growth rates in China, continuing weakness of the Eurozone sector, the
strength of the US dollar, the fall in Australian interest rates, iron ore prices
recently dipping below US$50/tonne and WTI oil prices below US$50/bbl. I could
go on, but they all result in market volatility and a loss of confidence in the
resource sector and have an impact on KGL. The simple fact is, that it is currently
a very difficult world in which to make long term business plans.
Having said that, I can tell you that we have had preliminary discussions with a
number of potential Project partners. However, In order to achieve the best
possible outcome for shareholders, we have held off progressing the search for a
partner until the revised PFS information is available.
So in summary. KGL's Jervois Project is in very good shape and on track to deliver
a successful revised PFS towards the end of this year. We do have the funds to
complete all of our current scheduled PFS work at Jervois but will need funding for
the next stage of the Project’s development. Although the investment market for
resource companies in Australia remains uncertain. Jervois is an outstanding
project and I am confident that it is on track to be developed into an operating
mine.
In closing I would like to thank Simon and his team and my fellow directors for
their support and hope that you as shareholders share our excitement about the
future of the Jervois Project and our Company.
AGM 29 May 2015
1
1. Jervois Copper PFS Optimisation
2. Exploration Plans
2
Jervois Project Setting
On the Plenty Highway
Concentrate to be trucked from
site to Alice Springs then
transported by rail to Darwin port
In the 1960’s, ore was trucked
from Jervois to Mt Isa
3
Reward Prospect looking south
4
4
Geological Setting
•
•
•
5
Hosted by Bonya Metamorphics in
Eastern Arunta
Northerly Plunging Syncline
Hybrid SEDEX-VMS
Deep Drill Hole
Mineralisation intersected
870m below surface
Copper mineralisation
6
Lead and Zinc mineralisation
Mineral Resources Update
25.3 Mt @ 1.1% Cu for 280,000 t Cu
25.3 Mt @ 22 g/t Ag for 18 Moz Ag
25
450,000
400,000
350,000
Million Ounces
300,000
Copper Metal (tonnes)
20
+64%
250,000
200,000
150,000
100,000
+61%
15
10
5
50,000
0
May 2011
July 2011
Copper Indicated
7
Jan 2012
Nov 2012 Sep 2014
Copper Inferred
Exploration Potential
0
May 2011
July 2011 Jan 2012
Silver Indicated
Silver Inferred
Nov 2012 Sep 2014
Exploration Potential
The potential quantity and grade of the Exploration Potential is conceptual in nature and there has been insufficient exploration to define a Mineral Resource. It is
uncertain if further exploration will result in the determination of a Mineral Resource.
High Grade Resources
1.6
Mutooroo
Australian Copper Mines and Projects
(open pit only)
1.4
1.2
Jervois
Copper Grade (%Cu)
1.0
Maroochydore
White Range
0.8
E1-Monakoff
Kanmantoo
Mt Elliott
Lady Annie
Einasleigh
0.6
Hillside
Kalkaroo
Kalman
0.4
Rocklands
Nanadie Well
Bushranger
Copper Hill
0.2
0.0
10,000,000
Roseby
Browns
Temora
100,000,000
Mineral Resources (tonnes, log scale)
Source: SNL Mining & Metals, Terra Studio. Most recent mineral resources available, copper only. Bubble size according to copper metal contained.
8
PFS Optimisation
9
Jervois Pre-Feasibility Study
Dec 2014
2 mtpa Flotation Plant
7 Year Mine Life
21,000 tpa Copper Production
1 M ozpa Silver Production
Initial Capex $189m
C1 cost US$1.51/lb*
* (After by-product credits and using an exchange rate of A$/USD
0.845 and silver price of USD 20/oz)
10
Additional Work Programme
The Jervois project’s value can be significantly increased by further drilling and
metallurgical work:
1.
2.
3.
4.
11
Geotechnical – Steeper Pit Walls
Metallurgy – Targeting increased recovery of Copper and Silver
Resource Drilling – Targeting known high grade areas
Operating Costs – Reductions in mining costs – cheaper diesel
1. Geotechnical Drilling
• 1,200 meters of diamond core drilling in to the planned pit walls
• Aim is to design steeper walls to reduce waste mining
• New zones of copper discovered in Eastern and Western walls at
Marshall
• Result – Pit Walls design angle increased from 47 to 51 degrees
12
2. Metallurgical Test work
Metallurgy test work designed to achieve the following: Increase the gold and silver recoveries
Increase the recovery of copper in the transitional zone
Test the production of a mixed lead and zinc concentrate
Also determined ore is softer (lower power consumption)
13
Improvements in Metallurgical Recovery
Additional metallurgical test work ongoing to further
enhance silver and copper recoveries.
Results to date indicate that we can expect a
significant improvement in silver recovery and some
improvement in both copper and gold recovery.
14
3. Resource Drilling
• 11,000m Resource
Drilling Completed
15
Bellbird East
16
Reward North
17
4. Operating Costs
Updated pricing received for open pit and underground mining costs
Processing operating costs reduced due to lower power consumption
~$4m per year saving
Cheaper diesel fuel price will result in substantial savings
~$9m per year saving at current prices
18
Exploration
19
Exploration
CSIRO Research Project conclusion – SedEx-VMS Hybrid
SedEx deposits generally large
Mineralisation is polymetallic
Folded repetitions within north plunging syncline
Deep drilling programme to test the down dip potential of the three main
deposits at Marshall-Reward, Bellbird and Green Parrot
20
Reward
Large EM conductor
at Reward to be
tested by diamond
drilling
SURFACE
CONDUCTOR
2m @ 12.02% Pb and 473 g/t Ag
7m @ 0.6% Cu, 4.25% Pb, 2.98% Zn and 53.4 g/t Ag
7m @ 2.07% Cu, 1.06% Pb, 2.41% Zn, 92.1g/t Ag, 0.18g/t Au from 1100m
Including
2m @ 4.75% Cu, 1.68% Pb, 1.94% Zn, 156.1g/t Ag, 0.25g/t Au from 1105m
21
RJ169
72m @ 3.27% Cu,
51.22 g/t Ag and
1.16 g/t Au
Reward
If EM target is
successful then
daughter holes to
be drilled.
Second deep hole
to be drilled 300m
along strike to the
south of first deep
hole.
22
Bellbird 3DIP
Bellbird Mineralisation
responds well to Induced
Polarisation (IP)
3DIP survey designed to
identify sulphides in zones
along strike and parallel to
Bellbird to depths of over
500m
Inclusion of Magnetotelluric
(MT) acquisition extends
this to over 1000m depth
23
Bellbird
Three deep diamond
holes to be drilled
approximately 300m
below the base of the
Bellbird deposit.
Targeting will be
optimised with 3DIP
results
24
Green Parrot Long Section
Five deep RC
holes to be drilled
100m below the
base of the Green
Parrot resource
Successfully
drilling deep RC
holes
In most recent
program 532m
was achieved
25
Green Parrot Cross Section
26
Soil Sampling and RAB drilling
Completing the
geochemical picture
Soil Sampling in areas
of subcrop &
RAB Drilling in areas of
transported cover
27
Schedule
1,200m Diamond Core Geotechnical Drilling Completed in March 2015
11,000m Resource Drilling Programme Completed April 2015
Metallurgical Test work – Nearing Completion
Resource update scheduled for July 15
Updated Pre Feasibility Study October 15
Exploration Programme June to Dec 2015
28
For more information contact
Simon Milroy on +61 7 3071 9003
or info@kglresources.com
or visit www.kglresources.com
ASX code: KGL
Level 7, 167 Eagle Street
Brisbane, QLD 4000
AUSTRALIA
Forward-Looking Statements:
This presentation includes certain “Forward-Looking Statements”. All statements, other than statements of historical fact, included herein, including without
limitation, statements regarding forecast cash flows and potential mineralisation, resources and reserves, exploration results and future expansion plans
and development objectives of KGL Resources are forward-looking statements that involve various risks and uncertainties. There can be no assurance that
such statements will prove to be accurate and actual results and future events could differ materially from those anticipated in such statements.
The Jervois Resources information was first released to the market on 15 September 2014 and complies with JORC 2012. The company confirms that it is
not aware of any new information or data that materially affects the information included in the original market announcement and that all material
assumptions and technical parameters underpinning the estimates in the relevant market announcement continue to apply and have not materially changed.
The company confirms that the form and context in which the Competent Person’s findings are presented have not been materially modified from the
original market announcement.’
29
Hole
Date originally Reported JORC Reported Under
RJ
169
7/09/2011
2004
KJD010W1
15/01/2015
2012
KJC
162
28/05/2015
2012
KJC
163
28/05/2015
2012
KJC
136
28/05/2015
2012
KJC
138
28/05/2015
2012
KJC
140
28/05/2015
2012
JORC Compliance Statement
The drilling results reported under JORC 2004 have not been updated since to comply with the
JORC Code 2012 on the basis that the information has not materially changed since it was last
reported.
The Jervois Resources information was first released to the market on 15 September 2014 and
complies with JORC 2012. The company confirms that it is not aware of any new information or
data that materially affects the information included in the original market announcement and that
all material assumptions and technical parameters underpinning the estimates in the relevant
market announcement continue to apply and have not materially changed. The company confirms
that the form and context in which the Competent Person’s findings are presented have not been
materially modified from the original market announcement.’
The Jervois Pre-Feasibility Results were first released to the market on 8 December 2014 and
complies with JORC 2012. The company confirms that it is not aware of any new information or
data that materially affects the information included in the original market announcement and that
all material assumptions and technical parameters underpinning the estimates in the relevant
market announcement continue to apply and have not materially changed.